Project Name: Operation Connect - Q3 2025 Team Offsite
Reporting Period: Week 3; June 15 - June 19, 2025
Prepared By: Deborah Iyanuoluwa Ajao
Date: June 19, 2025
Submitted To: HR Director, Vitalbridge Technologies Ltd
| Area | Status | Comments |
|---|---|---|
| Schedule | On track | Travel and accommodation confirmed ahead of June 20 deadline |
| Budget | At risk | Travel costs for 2 team members from Abuja exceeding per-person cap; under review |
| Scope | On track | No scope change requested |
| Vendors | On track | Catering vendor selected and contract under Finance review |
| Attendance | On track | Attendee list confirmed for all 15 team members. |
| Vendor | Services | Status | Notes |
|---|---|---|---|
| La Champagne Tropicale | Accommodation and conference | Confirmed | Contract signed. Deposit payment initiated. |
| Flavors by Adaeze | Meals and refreshments | In progress | Contract under finance review. Approval expected June 20 |
| Transport | Team and Travel coordination | Confirmed | 13 of 15 bookings confirmed. 2 Abuja members pending |
| Activities | Team building activities | In progress | Team building activities shortlisted |