The goal of this page is the planning of the project timeline and setting soft milestones. See below for an example of the final project.
NOTE: First Draft - Not final nor indicative - created not knowing anything!
Timeframe | Phase | Tasks | Deliverables | Notes/ Comments | Specific Deadline | Planning Fallacy adjusted Deadline (x1.5) |
---|---|---|---|---|---|---|
End: 22-12-2021 | Conceptualisation | Problem Structuring | ||||
Definition of Scope of the Project | ||||||
Initial scoping of use cases | ||||||
PI solution relative to other solutions | Problem-Definition sheet | |||||
Use Case document | ||||||
PI documentation doc | ||||||
PI Comparative Analysis to other Industry Solutions | ||||||
Workspace set up | ||||||
Squad definition | Potentially useful Stakeholder Mapping and Analysis | |||||
End: 31-01-2021 | Design Phase | Decision on features of PI iteration 1 | Decide on what features are needed for PI v1 | |||
End: 29-02-2021 | Validation Phase | Simulation & Modelling of PI | ||||
Iterating as needed | ||||||
End: 15-03-2021 | Finalisation Phase | Documentation of PI | ||||
Updated Github | ||||||
A final report documenting findings and analysis of simulations | ||||||
Deployment phase | Curve Labs? | |||||