Project Name: Tendara — Caregiver Matching Mobile App
Reporting Period: Week 3 — April 11 to April 17, 2025
Prepared By: Deborah Iyanuoluwa Ajao, Project Manager
Report Date: April 17, 2025
Submitted To: Co-founder, Vitalbridge Technologies Ltd
Overall project status
Accomplishments this week
- UI/UX Design sprint commenced April 11 as planned
- Family booking flow wireframes completed by Designer; April 15
- First design review session held with Vitalbridge co-founder; April 17
- CR-001 — in-app messaging request formally reviewed and rejected by project sponsor following PM impact analysis presentation. Contact request feature confirmed as MVP communication solution
- Backend Developer commenced database schema planning based on confirmed requirements
- Payment gateway API documentation received and reviewed by Backend Developer -integration approach confirmed
- Sprint 1 planning meeting held — Sprint 1 covers UI/UX Design completion and backend schema planning
Planned for Next Week
- Complete all UI/UX wireframes by April 20
- Obtain final client design approval from Vitalbridge by April 20
- Begin frontend development on approved screens — April 21
- Begin backend development — April 21
- Sprint 1 review and Sprint 2 planning — April 24