Project Name: Tendara — Caregiver Matching Mobile App
Reporting Period: Week 4 — April 18 to April 24, 2025
Prepared By: Deborah Iyanuoluwa Ajao, Project Manager
Report Date: April 24, 2025
Submitted To: Co-founder, Vitalbridge Technologies Ltd
Overall Project Status
Accomplishments this week
- All UI/UX wireframes completed by Designer — April 18
- Final design review held with Vitalbridge co-founder — April 19
- Full design approval received from client — April 20; on schedule
- Frontend Development commenced — April 21
- Backend Development commenced — April 21
- Sprint 1 Review held — April 24; all Sprint 1 deliverables completed and demonstrated to client
- Sprint 2 Planning held — April 24; Sprint 2 covers frontend and backend development
Planned for Next Week
- Complete family and caregiver registration screens
- Complete user authentication APIs
- Begin booking flow screens and booking management APIs
- Daily standups continue at 9am
- Mid-sprint check-in with Vitalbridge co-founder; April 28