WEEK 1 PROJECT STATUS REPORT
Project Name: Tendara - Caregiver Matching Mobile App
Reporting Period: Week 1; April 1 to April 3, 2025
Prepared By: Deborah Iyanuoluwa Ajao
Report Date: April 3, 2025
Submitted to: Co-Founder, Vitalbridge Technologies Ltd
Overall Project Status
Accomplishments this week
- Project kickoff meeting held on April 1 with full team and Vitalbridge Technologies Ltd co-founder in attendance
- Project charter reviewed, agreed and signed off by project sponsor
- MVP scope, timeline, budget and team responsibilities formally communicated to all team members
- Communication plan activated; daily standup schedule confirmed at 9am
- Project workspace set up in Notion with task tracker, risk register, stakeholder log and project documentation
- Requirements gathering officially commenced on April 1 with initial discovery session held with Vitalbridge co-founders
- Third party payment gateway provider shortlisted; confirmation expected by April 5
Planned for next week
- Complete requirements gathering and document all functional and non-functional requirements by April 10
- Conduct second discovery session with Vitalbridge co-founders to validate requirements
- Obtain formal client sign-off on requirements document before UI/UX Design begins
- Confirm third party payment gateway provider