Project: Tendara - Caregiver Matching Mobile App

Meeting Type: Sprint 3 review and sprint 4 planning meeting

Date: May 15, 2025

Time: 9:00am

Facilitator: Deborah Iyanuoluwa Ajao

Attendees

Role Present
Project Manager Yes
Project Sponsor Yes
UI/UX Designer Yes
Backend Developer Yes
Frontend Developer Yes
QA Tester Yes

Sprint 3 review

Sprint Goal Achieved: Yes — all screens, APIs and integration completed on schedule.

Deliverable Demonstrated Client Feedback Decision
Contact request flow screens Yes Approved- praised as elegant solution No changes
Push notification screens Yes Approved No changes
Ratings and reviews screens Yes Approved No changes
Caregiver earnings dashboard Yes Approved No changes
Caregiver verification workflow Yes - internal demo Approved No changes
Admin dashboard Yes - internal demo Approved No changes
Full integration Yes Approved Ready for QA

Sprint 3 Retrospective

What Went Well What Could Be Improved Action for Sprint 2
Integration completed ahead of schedule
Client praised contact request flow solution — validates CR-001 decision

Sprint 4 Planning

Sprint Goal: Complete Testing and QA, resolve all bugs, conduct UAT, obtain sign-off and submit to app stores.

Sprint 4 Backlog committed

Task Assignee Completion Estimate
Full QA testing QA tester 5 days
Major and minor bug resolution Frontend and Backend Developer 3 days
Regression testing QA tester 2 days
UAT session coordination PM 1 day
UAT execution PM, Project sponsor, Beta users 2 days
UAT bug fixes Backend and Frontend Developer 1 day
App store submission preparation Backend Developer 3 days
Google Play and Apple App Store submission Backend Developer 1 day
Post-launch stabilization monitoring All team members 2 weeks

Next Meeting Date: May 18, 2025

Time: 9:00am

Agenda: Daily standup meeting

UAT session: May 21-22, 2025