Project Name: Tendara — Caregiver Matching Mobile App

Project Duration: April 1 to May 31, 2025

Report Date: May 31, 2025

Prepared By: Deborah Iyanuoluwa Ajao, Project Manager

Submitted To: Co-founder, Vitalbridge Technologies Ltd

Executive Summary

Tendara — Caregiver Matching Mobile App was successfully designed, developed, tested and launched within scope, on schedule and under budget. The Tendara MVP was submitted to and approved by both the Google Play Store and Apple App Store on May 31, 2025 — the agreed target launch date. The project was delivered with zero critical bugs at launch, full UAT sign-off from Vitalbridge Technologies Ltd and a final spend of ₦2,500,000 against a budget of ₦2,800,000 — ₦300,000 under budget. The project is formally closed as of May 31, 2025.

Project Summary

Item Detail
Project Start Date April 1, 2025
Project End Date May 31, 2025
Total duration 8 weeks
Total budget #2,800,000
Total spend #2,500,000
Budget variance #300,000 under budget
Sprints completed 4
Critical bugs at launch 0
UAT Participants 10
UAT sign-off Received May 23, 2025
App store launch May 31, 2025 - on schedule

Project Objectives Review

Objective Target Result Status
Deliver Tendara MVP on iOS and Android May 31, 2025 Launched May 31, 2025 ✓ Achieved
Complete within budget ₦2,800,000 ₦2,500,000 spent ✓ Achieved
Zero critical bugs at launch 0 0 critical bugs ✓ Achieved
UAT sign-off from client Required Received May 23 ✓ Achieved
All tasks completed on schedule 8 tasks 8 tasks completed ✓ Achieved

Sprint summary

Sprint Duration Goal Outcome
Sprint 1 April 11-24 UI/UX Design and backend schema ✓ All deliverables completed and approved
Sprint 2 April 25 - May 8 Core screens and APIs ✓ All deliverables completed. Payment gateway resolved
Sprint 3 May 9-10 Remaining screens, APIs and integration ✓ All deliverables completed ahead of schedule
Sprint 4 May 11-31 Testing, QA, UAT and launch ✓ Zero critical bugs. UAT passed. Live on schedule

Change request summary

CR Number Description Decision Impact
CR-001 Client requested full in-app messaging and media sharing added to MVP Rejected — deferred to Phase 2 Timeline and budget protected. Contact request feature implemented as alternative

Risk summary

Risk Status Outcome
App store rejection Resolved Guidelines reviewed Week 6. No compliance issues. Both stores approved
Payment gateway integration delays Resolved 2-day delay in Week 5 absorbed within sprint buffer
Scope creep from client Resolved CR-001 formally rejected. MVP boundary maintained
Caregiver verification complexity Resolved Simplified to manual upload for MVP. Automated in Phase 2
Client feedback delays Resolved All feedback received within 48-hour SLA throughout project
MVP scope too large Resolved Core booking flow prioritized. All features delivered within 8 weeks
Single point of failure Monitored Technical documentation maintained throughout. No team member loss
Families bypassing platform Monitored Contact request feature implemented. No public contact display
Platform data exposure Monitored NDPR and GDPR compliance built into product from Week 1

Budget Final Reconciliation

Category Budgeted Actual Spend Variance Status
UI/UX Design ₦500,000 ₦500,000 ₦0 🟢 On Budget
Development ₦1,200,000 ₦1,150,000 ₦50,000 🟢 Under budget
Testing and QA #300,000 #280,000 #20,000 🟢 Under budget
Project Management #200,000 #200,000 #0 🟢 On Budget
Marketing #400,000 #370,000 #30,000 🟢 Under budget
Contingency #200,000 #0 #200,000 🟢Unused
Total #2,800,000 #2,500,000 #300,000 🟢 Under budget

Recommendations for Tendara Phase 2