Project Name: Operation Connect - Q3 2025 Team Offsite

Reporting Period: Week 1; June 1 - June 5, 2025

Prepared By: Deborah Iyanuoluwa Ajao

Date: June 5, 2025

Submitted To: HR Director, Vitalbridge Technologies Ltd

Overall Project Status

Area Status Comments
Schedule On track Project kicked off successfully. All Week 1 tasks completed on schedule
Budget On track No expenditure recorded. Budget intact at #5,000,000
Scope On track Project scope confirmed and signed off by HR Director
Vendors At risk Venue shortlisting in progress - 3 venues identified, awaiting availability confirmation
Attendance On track Attendee list requested from HR Director - expected by June 10

Accomplishments this week

Planned for Next Week