1. Roadmap with main deliveries

  2. Break them down into one-person deliveries, and in each include:

    a. Visual example of how it should be seen when done

    b. List of assumptions that it should be able to do when done

    c. What would be the evidence of completion? (MOV, PDF, JPG, Code)

    d. Pre-requisites to start the task

    e. Critical path (which tasks are dependent of this task to be finished in order to start?)

    f. List of skills needed to perform this task (this will be used to mint the badges when done)

    g. Expected time required to complete the task

    h. To whom should the person taking the task should contact when finished, and in case of doubts (direct link to the person)

    An example is this:

    Milestone:

    1. Operational minting dashboard:

    Main Delivery:

    1.1 Working Smart contract

    Single Delivery from Engineering:

    1.1.E1 IPFS; 1.1.E2 Smart contract; 1.1.E3 API; etc

    1.1.E1 IPFS:

    a. An image of how should the IPFS should look once connected

    b. List of assumptions needs to do when its ready.

    ...

    1.1.E2 Smart contract:

    a. ...

    Single Delivery from Product:

    1.1.P1 Responsive UX; 1.1.P2 Domain for landing page; etc,

    ...